A case study about our expertise at work in the Industrial sector
Power Management Design and Build was called in by KpH Environmental Services Ltd to work on the 11kV network for 20 Old Bailey, London EC4M 7BH, a prestigious office address opposite the Central Criminal Courts in London.
Kph Environment Services was commissioned to remove mechanical and electrical services ahead of the new fit out works by ISG plc, the prime contractor for Blackstone.
Our project included visits by one of our Senior Authorised Persons and one of our Authorised Persons to assess the status of the high voltage switchboard which fed the 4 x 11kV transformers.
Switching operations were undertaken to suit the schedule of works. One 11kV transformer was isolated and earthed and we issued the necessary documentation to allow the safe disconnection and removal of the associated low voltage switchboard.
A second transformer was restored to operation so that there would be sufficient lighting on the upper floors to allow strip out works to be undertaken safely. All of the High Voltage switching operations were completed across a Bank Holiday weekend.
The result was the successful completion of the electrical services for KpH Environmental Services, enabling ISG to make a prompt turnaround to the £59million scheme.
Video is included for illustrative purposes only. Power Management Design and Build cannot be held responsible for content held on external websites.